PDA

View Full Version : +/-AverageNode


JFFORTIN
07-19-2004, 09:33 PM
Lm on maya 6 and everytime l change the plus minus operation maya crash.even if my nide is connected or not l got that problem.Is someone get that Prob ?

CIM
07-20-2004, 03:37 AM
A bunch of Maya's nodes, in 6.0, seem to be buggy and will cause crashes. I suggest you simply send bug reports (on Alias' site) directly to Alias.

augustus
07-20-2004, 05:54 AM
While waiting a patch, you can change operation via command line using setAttr mel command. Like this:

setAttr plusMinusAverage1.operation 2

1 for plus, 2 for minus and 3 for average

JFFORTIN
07-20-2004, 09:06 AM
yep its what l done augustus.......change via mel.................ill send that to alias.

JFFORTIN
07-20-2004, 06:05 PM
nah mel doesnt work still have that problem :(
what l do to get rib of that problem is go back to maya 5 to setup my scene with that node

mrgoodbyte
07-20-2004, 06:30 PM
Did you try hardcoding? Meaning just writing the value into the .ma file? Does that work?

augustus
07-20-2004, 07:02 PM
nah mel doesnt work still have that problem :(
what l do to get rib of that problem is go back to maya 5 to setup my scene with that node
Strange. I did before and worked

JFFORTIN
07-20-2004, 07:10 PM
l didnt try that ............l need to do some test and try so l cannot do that everytime..........lm usinf maya 5 its fine for now

CGTalk Moderation
01-18-2006, 06:00 PM
This thread has been automatically closed as it remained inactive for 12 months. If you wish to continue the discussion, please create a new thread in the appropriate forum.